Design the infrastructure for the redeveloped urban area.
STATUS: Complete
PROJECT
ASSIGNEE
CATEGORY
Design
PRIORITY
High
BUDGET
$ 1.5M
START
2024-05-07
DURATION
90 days
DAYS UNTIL DEADLINE
0 DAYS
ESTIMATED END DATE
2024-08-05
ACTUAL END DATE
2024-09-02
DAYS OVERDUE
28 DAYS
Available: 0 | In use: 3 | Scheduled: 0
Available: 3 | In use: 0 | Scheduled: 0