πŸ”‘ Logged in as ****

πŸ› οΈ 🟒 Infrastructure Design (T-202361URBAN-7)

Design the infrastructure for the redeveloped urban area.

STATUS: Complete

β“˜ General information

ℹ️ Information

PROJECT

ASSIGNEE

CATEGORY

Design

PRIORITY

High

BUDGET

$ 1.5M

⏱️ Timing

START

2024-05-07

DURATION

90 days

DAYS UNTIL DEADLINE

0 DAYS

ESTIMATED END DATE

2024-08-05

ACTUAL END DATE

2024-09-02

DAYS OVERDUE

28 DAYS

πŸ—οΈ Required equipment

Available: 0 | In use: 3 | Scheduled: 0

Available: 3 | In use: 0 | Scheduled: 0

⚑ Task actions

Made with Baserow